Garsy boosts production capacity by 40 percent thanks to QRM and investment in machinery

Garsy produces metal structures for plants in public spaces. Expanding, while continuing to deliver on time or even faster was a major challenge for the future and the company wanted to tackle it as quickly as possible. They do so through investments and QRM.    

The dynamic SME Garsy in the Kempen town of Malle specialises in the production of metal street furniture which can be combined with plants. The product range includes edges, flower towers, greenwalls and planters. These are typically used in public spaces, project construction, roof and city gardens.

The product range is characterised by a high degree of customisation. Even though there are several standard products, each product is different, often because of its dimensions. The products are mainly made of Corten steel and bright steel, which is shaped by cutting, folding, rolling, welding, lacquering and galvanising. Garsy has a few machines at its disposal for this purpose, but depends on suppliers for the finishing.

Growth, lead time and delivery terms

The company has grown in recent years and Garsy expects further growth for the coming years. In order to simultaneously continue to meet the expectations of customers, the company wanted to optimise the production and support processes.
An important point of attention in this respect was a drastic reduction of the lead times. Average delivery times usually were 4 to 6 weeks and meeting the delivery deadlines was often problematic. However, customers were increasingly demanding short(er) lead times.

One of the difficulties often faced by Garsy is that they are typically called in towards the end of a construction project, when the outdoor spaces need finishing. Due to this late involvement, the time pressure for timely delivery, often in addition to delays already suffered by the construction project, the supplier is often under heavy pressure.

In addition to shortening the lead time for the entire process, Garsy wanted to identify the potential for improvement in the production and supporting processes. After all, shortening the lead time alone was difficult to achieve due to the dependence on external parties.

Implementation of QRM

The company contacted Sirris and that is how they ended up at QRM. The Sirris experts performed an analysis of the existing situation for the main products in the range, some of which are custom-made. Measurements showed that make-to-order and make-to-measure products in particular often have a long lead time. The lead time and workshop equipment were reviewed.

An adapted layout was considered in order to reduce walking and transport distances and possibly also improve the working atmosphere and productivity. Operations were grouped on the shop floor. It was also suggested that a small part of the capacity should deliberately not be fully planned, in order to create a reserve and avoid having to postpone promised orders. In order to achieve the necessary flexibility in production, cross training was also used to teach more employees to weld. Thanks to the spare capacity and flexible production operators, the production process can also go more smoothly.

Garsy also decided to support the QRM method with specific planning software. The shorter lead times also make shorter delivery periods possible.

Strong investment in machinery

In addition to the roll-out of a QRM process, the analysis specifically looked into reducing the throughput times through investments in sheet metal working machines and CAD/CAM. Garsy largely depended on suppliers for its laser cutting and most of the folding work. The company's own machinery for sheet metal working consisted of a plate shears and a folding bench, which was too limited to make the products. Moreover, the folding bench was already quite old and not equipped with NC control, so everything had to be set manually. This meant extremely high conversion times, which made it impossible to operate this machinery in a profitable manner.

The need to invest in new sheet metal working machines and, in particular, to produce customised products in-house, became more tangible. In addition to the gains in lead time, more flexible designs, and therefore new products, would also become possible. An additional advantage was that spare or extra parts for an ongoing project can be made quickly. Sirris guided the company in selecting the most suitable machinery for its products and production.

In the course of 2017 Garsy already reduced its lead time by approximately 30 percent. The reduction in lead time was rather limited, because at the same time a 52 percent turnover increase was achieved. In addition, the production capacity increased by about 40 percent, and thanks to the interventions the current percentage of production orders is 96 percent on-time and there are now no more substantial differences in the punctuality of deliveries between standard orders and the unexpected, urgent orders.

Would you like to know more about QRM? The QRM World Conference will take place in Eindhoven on the 19th and 20th of June. This conference includes a series of hands-on workshops and testimonials from companies that have achieved success with QRM. On 21 June there will be an opportunity to visit various QRM companies. Prior to the conference, on 18 June, Rajan Suri - the creator of QRM - will be giving a QRM masterclass.